Ralph Wilson Stadium Improvements

Technology

1. Expansion of live game sound into concourse restrooms $ 601,000
2. New HD Video Display system to east end zone   8,764,000
3. Expanded video control room including full conversion to High Definition   5,092,000
4. Upgraded Tele/Data infrastructure to meet modern requirements   6,604,000
5. New data distribution system to support IPTV and distributed TV monitors   4,194,000
  $ 25,255,000

Upgrades – Ingress, Egress, Circulation, Restrooms and Food Service

6. East End Zone Renovation including main concourse expansion and addition of a new commissary building $ 8,331,000
7. Intentionally Omitted.    
8. Intentionally Omitted.    
9. New destination concession and restroom areas on the upper concourse   4,442,000
  $ 12,773,000

Branding - Front Profile, Team Store, Way finding and Sponsor Activations Plaza

10. Relocation and expansion of Team Store to the new west end plaza $ 2,641,000
11. New stadium entry plazas including wrought iron security fence   7,108,000
12. Steel canopies for new stadium entry plazas   1,083,000
13. Enhanced graphics and way finding throughout entire stadium and gates   3,197,000
  $ 14,029,000

Thorough Renovation of Present Space

14. Various infrastructure repairs and maintenance items $ 10,451,000
15. Refurbish and enhance existing press box area   706,000
16. Concourse life safety improvements to enhance code compliance   1,195,000
17. Install galvanized intermediate aisle rails in upper bowl   954,000
18. New fire alarm detection and notification system in Training Facility   210,000
19. Add ADA compliant wheelchair seating in 300 level seating areas   165,000
20. Add ADA compliant wheelchair seating in east and west end zones   609,000
21. Install handrails on both sides of vomitory ramps on main concourse   1,011,000
22. Cosmetically upgrade and refurbish all existing toilet rooms   3,938,000
23. Renovate concession stands to meet modern requirements   4,067,000
24. New equipment for renovated concession stands   3,923,000
25. Deploy full POS system for all existing and new concession stands   1,564,000
26. Renovation of post-game interview room, field tunnel and storage areas   835,000
27. Intentionally Omitted    
28. Upgraded lighting throughout the main concourse   797,000
29. Relocate writing press to tower club and convert old press box to 50yard line club   2,256,000
30. Repurpose operations area to field level staging area   1,012,000
31. Cosmetically upgrade stadium suites   5,760,000
32. Add radiant heat to sideline club seats and newly added areas of main and upper concourse   966,000
33. Renovation of Time Warner tower club area   1,606,000
34. Intentionally Omitted    
35. Enhanced tailgate experience in parking lots   637,000
  $ 42,662,000

Team Areas

36. Training facility modernization through expansion and upgrades $ 7,684,000
37. New operations and storage complex   3,707,000
  $ 11,391,000
SUB - TOTAL: $ 106,110,000
A/E Fees: $ 8,519,000
Other Soft Costs: $ 2,371,000
PROJECT CONTINGENCY RESERVES: $ 13,000,000
     
TOTAL: $ 130,000,000